PROJECT AUTHORIZATION PACKET ID: PMT-M0N6
CONTRACT ID EMARS PROGRAM CODE AUTHORIZATION NO:
9224202D      92242 4
It is hereby ordered that the project herein described be undertaken and accomplished within the funding level authorized.
PROJECT ID PROJECT ID NUMBER FEDERAL PROJECT NUMBER 6 YR PLAN ITEM NUMBER 6 YR PLAN ITEM PARENT NUMBER


NHPP 3020007

02-01088 2-.-
PROJECT TYPE PROJECT LENGTH NUMBER OF BRIDGES SYSTEMS
NEW ROUTE MI
PROJECT PHASE
&
RESPONSIBILITY
PLANNING DESIGN RIGHT OF WAY UTILITIES
CONSTRUCTION TITLE DEEDED TO: MAINTENANCE OTHER
FUNDING & TIME
ACCOUNTABILITY
PARTICIPATING AGENCIES
FEDERAL FHWA STATE KYTC LOCAL OTHER
REQUESTED FUNDS FOR THIS AUTHORIZATION
ITEM NUMBER PHASE FUND PROGRAM FEDERAL FISCAL YEAR STATE FISCAL YEAR
FEDERAL APPR
CODE
CURRENT FUNDING REQUEST
2-1088.2 D 1200 FD52 2021 2021 Z001 $7,200,000.00
2-1088.2 D 1100 FD52 2021 2021 $1,800,000.00
CURRENT FUNDING REQUEST TOTAL: $9,000,000.00
AUTHORIZATION SUMMARY FOR THIS 10-1 SERIES
PHASE TOTAL AUTHORIZATION TO DATE (INCL. CURRENT REQUEST)
PLANNING $3,220,000.00
DESIGN $15,000,000.00
UTILITIES $0.00
R/W $65,000.00
CONSTRUCTION $0.00
NON-HIGHWAYS $0.00
  Total: $18,285,000.00
REMARKS: THIS AUTHORIZATION PROVIDES $7,200,000 OF FEDERAL NH FUNDS WITH $1,800,000 OF 20% STATE MATCHING FUNDS TOTAL OF $9,000,000 FOR CONTINUATION OF PE AND ENVIRONMENTAL ACTIVITIES.
 
Project Approval Recommended By:
James Ballinger   10/12/2020
Signed and Approved by:
Jim Gray   10/13/2020
AUTHORIZATION LOCATION
ITEM NO. COUNTY DIST FACILITY NAME
ROUTE LENGTH SCOPE
02-01088.20 HENDERSON


2 HENDERSON, KY- EVANSVILLE, IN MI CONSTRUCT THE PORTION OF THE I-69 ORX PROJECT FROM THE HENDERSON BYPASS (KY 425) TO US 60. (100% KY SHARE) (2020CCR)